JBM Ecolife Mobility Surat Private Ltd ., In re
Date: November 2, 2025
Subject Matter
Liquidated Damages Paid for Breach of Electric Bus Operation Contract Are Not Subject to GST
Summary
M/s JBM Ecolife Mobility Surat Private Ltd. (the Applicant), an SPV, operates and maintains 150 BRTS AC Electric Buses for Surat Municipal Corporation (SMC) under a Concession Agreement (later tripartite with Surat Sitilink Limited - SSL). The agreem…
FULL TEXT OF THE ORDER OF AUTHORITY FOR ADVANCE RULING, GUJARAT M/s. JI3M Ecolife Mobility Surat Private Ltd., Plot No.-70, 13RTS Bus Depot, and Workshop, TP Scheme No-48, Opp Unn-I3hestan Urban I Icalth Centre, 13hestan, Surat [for short — ` applicant'[ is registered under GSI’ and their GS1’1N is 24AAFCj4549P1. Z1. 2. The applicant has stated that they are engaged in providing mobility sol…