Transmission Corporation of Andhra Pradesh Limited ., In re
- Court:
- Authority for Advance Ruling
- Bench:
- Andhra Pradesh
- Date:
- May 9, 2024
- Type:
- Advance Ruling
- Members:
- K. Ravi Sankar, B. Lakshmi Narayana
Subject
GST is leviable on amount recovered as liquidated damages from the suppliers or contractors due to breach of contract or non-performance within the stipulated period
Summary
The case law discusses the treatment of liquidated damages under contract law and the applicability of Goods and Services Tax (GST) on such damages. It highlights that liquidated damages, being pre-determined compensation in the event of breach of co…
Judgement
FULL TEXT OF THE ORDER OF AUTHORITY FOR ADVANCE RULING, ANDHRA PRADESH (Under sub-section (4) of Section 98 of Central Goods and Services Tax Act, 2017 and sub-section (4) of Section 98 of Andhra Pradesh Goods and Services Tax Act, 2017) 1. At the outset we would like to make it clear that the provisions of CGST Act, 2017 and APGST Act, 2017 are in parimateria and have the same provisions in…