Case LawTSAAR Order No. 10/2023
TPSC (India) Private Limited ., In re
- Court:
- Authority for Advance Ruling
- Bench:
- Telangana
- Date:
- April 16, 2023
- Type:
- Advance Ruling
- Members:
- S.V. Kasi Visweswara Rao, Sahil Inamdar
Subject
No GST on liquidated damages
Transition
Summary
The applicant, a works contractor, awarded a sub-contract to a company called DGAL for the construction of a thermal power project. Due to DGAL's inability to handle the agreed quantum of work, the applicant reduced the work allocated to DGAL and…
Judgement
FULL TEXT OF THE ORDER OF AUTHORITY FOR ADVANCE RULING, TELANGANA [ORDER UNDER SECTION 98(4) OF THE CENTRAL GOODS AND SERVICES TAX ACT, 2017 AND UNDER SECTION 98(4) OF THE TEALANGANA GOODS AND SERVICES TAX ACT, 2017.] 1. M/s. TPSC (India) Private Limited, A-1 Module, D-Quadrant, 2nd Floor, Cyber Towers, HITEC City, Madhapur, Hyderabad, Telangana -505081 (36AABCT1309H1ZN) has filed an applica…