AP Power Development Co. Ltd ., In re
DiscussDate: March 31, 2023
Court: Authority for Advance Ruling
Bench: Andhra Pradesh
Type: Advance Ruling
Judge(s)/Member(s): Ravi Sankar, R V Pradhamesh
Subject Matter
Liquidated damages attract GST
Summary
1. Whether liquidated damages collected by the APPDCL from CHETTINAD LOGISTICS PRIVATE LIMITED for non-performing of an act constitute as supply as per Section 7 of GST act. Answer : Affirmative 2. What is the classification under GST for such liquid…
FULL TEXT OF THE ORDER OF AUTHORITY OF ADVANCE RULING, ANDHRA PRADESH (Under sub-section (4) of Section 98 of Central Goods and Services Tax Act, 2017 and sub-section (4) of Section 98 of Andhra Pradesh Goods and Services Tax Act, 2017) 1. At the outset we would like to make it clear that the provisions of CGST Act, 2017 and SGST Act, 2017 are in parimateria and have the same provisions in like ma…