Chamundeshwari Electricity Supply Corporation Limited ., In re
Date: April 23, 2020
Subject Matter
Advance ruling cannot be given as the issue is pending before the Supreme Court
Summary
The issue of the exemption activities carried out by the applicant with reference to administration and Pre and Post connection charges towards supply of electricity is pending before Honorable Supreme Court of India vide SLP Diary No.s 24733/2019 da…
1. M/s Chamundeshwari Electricity Supply Corporation Limited, No.29, CESC Corporate Office, 2nd Stage, Vijayanagar, Near Hunsur Main Road, Hinkal, Mysuru- 570 017., having GSTIN number 29AACCC6636P1Z1, has filed an application for Advance Ruling under Section 97 of the CGST Act, 2017 read with Rule 104 of CGST Rules, 2017 and Section 97 of the KGST Act, 2017 read with Rule 104 of KGST Rules 2017,…