Gujarat Energy Transmission ., In re
- Court:
- Authority for Advance Ruling
- Bench:
- Gujarat
- Date:
- August 20, 2019
- Type:
- Advance Ruling
- Members:
- R B Mankodi, G C Jain
Subject
GETCO is also liable to pay 18% GST on recovery of charges viz. Pro-rata charges, Proportionate line charges, Operation and maintenance charges etc.
Summary
Q) Whether or not the cost of construction/ erection of Bays/ Sub-Stations, Overhead lines and Underground Cables and other charges including Pro-rata charges, supervision charges, proportionate line charges, registration fees and operation and maint…
Judgement
2. M/s Gujarat Energy Transmission Corporation Ltd., Sardar Patel Vidyut Bhavan, Race Course, Vadodara-390007 (herein after referred to as the “Applicant” or “GETCO” for the sake of brevity), vide Annexure ‘A’ sheet to their application dated 08.02.2018, specifically mentioned their queries as under: “Whether or not the cost of construction/ erection of Ba…